Program roadmap · February 2022 — December 2025

Alt‑Protein Mycelium Program

Drag the dashed tracer to move through time
{{ y.label }}
{{ mo.l }}
{{ ln.name }}
{{ p.t }}
Small Scale Pilot
Feb 2022 – Jun 2022
Strain Selection
A/B testing of foundational organism to produce mycelium biomass.
Small Scale Pilot
Jul 2022 – Jan 2023
Deviant Morphology
RCA efforts to establish provenance of unexpected deviant morphology that risked product quality.
Small Scale Pilot
Oct 2022 – Jan 2023
Grain Age Study
-
Small Scale Pilot
Jul 2023 – Mar 2025
Pasteurize vs Sterilize
Input, equipment, and process design of microbial knockdown methodology.
Small Scale Pilot
Jan 2024 – Dec 2024
Bioefficiency
Investigation in feedstock supplementation, environmental control, or pre-treatment for increase in bioefficiency. 
Large Scale Pilot
Jan 2023 – Jun 2023
Equipment Commissioning
Commissioning and testing of new large scale chamber system. Including SOP for controls, initiation, and turnover. 
Large Scale Pilot
Jan 2024 – Dec 2024
Scaled Production
Process improvement focused on material throughput and total volume output of team & system.
Jan 2024 – Jul 2024
Conditions Optimization
Large Scale Pilot
Dialing in core confounding variables of temperature, moisture, and airflow control for maximizing yeild.
Large Scale Pilot
Jul 2024 – Dec 2024
Pasteurize vs Sterilize
A/B testing of feasibility, economics, and throughput of feedstock microbial removal. Largest stage gate in the whole program
Large Scale Pilot
Dec 2024 – Mar 2025
Pre-treatment Plant Validation
In-house commercial continuous flow sterilization plant material testing and supplier validation.
Commercial Scale
Jan 2025 – May 2025
Technology Transfer
Culmination of process and full scale launch of in-house grown mycelium. Including on-site manufacturing.
Commercial Scale
May 2025 – Nov 2025
Co-manufacturing Site 1
Technology transfer to Canada co-manufacturing site. Including tech-transfer, training, and site remodeling.
Commercial Scale
Sep 2025 – Dec 2025
Down-stream Processing
Rebuilding production team of 7, process, and product specification of post harvest processing.
Commercial Scale
Nov 2025 – Dec 2025
Up-stream Processing
A/B testing & RCA of raw material site and handling to address intermittent quality assurance.
{{ tLabel }}
{{ tLabel }}
Feb 2022 – Dec 2025

Summary — Alt-Protein Mycelium Program — scale-up study

A program roadmap for an alt-protein mycelium platform, running February 2022 through December 2025 across three stages: small-scale pilot, large-scale pilot, and commercial.

The small-scale pilot covered strain selection by A/B testing of the foundational organism, a root-cause investigation into deviant morphology that threatened product quality, a grain age study, process and equipment design for microbial knockdown, and bioefficiency work on feedstock supplementation, environmental control and pre-treatment.

The large-scale pilot commissioned a new chamber system and its control SOPs, then pushed throughput and total volume output — dialing in the confounding variables of temperature, moisture and airflow, and running the pasteurize-versus-sterilize A/B on feasibility, economics and throughput. That comparison was the largest stage gate in the program. It closed with in-house continuous-flow sterilization plant testing and supplier validation.

Commercial scale was technology transfer: full-scale launch of in-house grown mycelium with on-site manufacturing, then transfer to a Canadian co-manufacturing site including training and site remodeling, a rebuild of the seven-person downstream processing team and its product specification, and upstream A/B testing and root-cause work on raw material handling to close out intermittent quality assurance issues.